This week we were able to pull together a consolidated schedule for all the IT development projects and could take a first look at the resource loading. It didn't look too bad because we had linked the tasks in such a way that resources would not be overloaded. Of course, this meant that some projects were scheduled to finish later than we had hoped but, since they were lower priority projects, that's the right thing.
Next week we'll start looking at status reporting on projects.
No comments:
Post a Comment