We also came up with a list of rules for the PMO to operate under:
The QPharma PMO will abide by the following rules
and norms:
- The PMO will operate under full transparency, sharing information with all interested parties
- Escalation principles will be published and followed
- Nobody works on projects past the research phase until the project is authorized by the steering committee
- Projects can be authorized outside the steering committee meetings by approval of a majority of members
- All projects within commercial operations require a charter. Professional operations can use a Statement of Work or Signed Contract as their charter
- Project Managers will hold weekly status meetings with their teams that last 30 minutes or less
- Project Managers will use Earned Value calculations to report on budget
- Project Managers will provide a weekly status report to the PMO every Wednesday
- Schedules require level of effort to be calculated for each activity
- The PMO will provide a monthly dashboard showing all project status to the steering committee prior to their monthly meeting
- The steering Committee will meet monthly
- Change control will be managed by the steering committee. The PMO head will facilitate the steering committee but the signatures of the majority of members are required to approve a project change
- PMO will meet weekly every Friday at 10 AM
- Bruce will publish PMO status reports
- PMO members will obtain their PMP certification by the end of 2014